Here is the schedule of things that have happened on the house so far:
July 14 cleared the property
July 17 Design Center meeting
July 27 laid in the pipes and prepped for slab
July 31 poured the slab
Aug 5 dropped off the bricks for the exterior walls
Aug 10 the exterior walls go up
Aug 13 the wood for the second floor and walls is dropped off on the property
Aug 27 hurricane Isaac brings lots of rain
Aug 31 the second floor beams and interior walls go up
Sept 3 Labor Day Holiday
the bulldozer was removing the grass and dirt and leveling the property out. we could see the actual property boundries.
ok, i had to get the kids into one of these pictures, the blocks are on the slab of the house.
front of the house, garage is on the far left.
wood framing goes up, second floor beams go up.
the interior, far left will be the kitchen, that beam of light shining in the middle will be the stair case